Pedestrian Bridges - Cudal and Manildra
Cudal Footbridge
Works for the new Cudal pedestrian bridge have now gone to tender, marking a significant step toward reinstating a valued connection across Boree Creek.
The original Cudal footbridge was a timber suspension structure linking the township with Dean Park via Taylor Street. For many years it provided a safe and convenient pedestrian connection, supported access to local recreational spaces, and served as an alternative route for nearby residents when low-lying crossings, such as Creek Street, were impacted by wet weather or changing creek conditions.
Since its removal, Council has worked with specialist engineers to investigate the site and develop options for a replacement bridge that is safe, accessible and better able to withstand future conditions. Community feedback has also played a key role in shaping the project, with a survey conducted in July 2025 showing strong support for a suspension bridge design, with 62 per cent of respondents selecting this option. The project is focused on restoring this important link for the community while incorporating improved design and resilience.

Manildra Footbridge
In Manildra, Council is also progressing plans to replace the pedestrian footbridge located in Kiewa Street. The bridge was an important part of the town’s local infrastructure, providing a safe and convenient crossing for pedestrians and supporting everyday movement between key areas of the community. Its loss has had a noticeable impact on connectivity within the town.
Since then, Council has been working to restore critical infrastructure and improve resilience across the local government area. The replacement of the Manildra pedestrian bridge forms part of this broader effort, ensuring essential community connections are reinstated and better prepared for future conditions
Funding
Both bridge projects are being delivered with support from government disaster recovery programs. The Cudal Footbridge is funded entirely through the Disaster Recovery Funding Arrangements (DRFA). The Manildra Pedestrian Bridge is primarily funded through the DRFA, with approximately 90 per cent of funding provided through the program and the remaining 10 per cent funded through the Regional Transport Resilience Fund (RTRF), jointly supported by the Australian and New South Wales Governments.
-
Join the Conversation
26 days agoShare Join the Conversation on Facebook Share Join the Conversation on X (formerly Twitter) Share Join the Conversation on Linkedin Email Join the Conversation linkIf you would like to ask a question or share feedback about this project, please use the space below.
We ask that all contributions are respectful, genuine and constructive. This forum is moderated 24/7 by an independent third party, and any inappropriate content may be removed.
Alternatively, you can email council@cabonne.nsw.gov.au(External link)(External link). Please include the project topic in the subject line so your enquiry can be directed to the appropriate team.
We look forward to hearing from you and working together on this project.
If you would like to ask a question or share feedback about this project, please use the space below.
We ask that all contributions are respectful, genuine and constructive. This forum is moderated 24/7 by an independent third party, and any inappropriate content may be removed.
Alternatively, you can email council@cabonne.nsw.gov.au(External link)(External link). Please include the project topic in the subject line so your enquiry can be directed to the appropriate team.
We look forward to hearing from you and working together on this project.
Go to discussionThank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends
No thanks
Lifecycle
-
Call for Tenders
Pedestrian Bridges - Cudal and Manildra is currently at this stage -
July 2026
this is an upcoming stage for Pedestrian Bridges - Cudal and ManildraThe tender for the design and construction of both pedestrian bridges has now been released, with outcomes expected to be reported to the July 2026 Ordinary Council meeting
-
August - September 2026
this is an upcoming stage for Pedestrian Bridges - Cudal and ManildraFinal designs prepared for construction and fabrication
-
October - November 2026
this is an upcoming stage for Pedestrian Bridges - Cudal and ManildraFabrication of bridge structures
-
December 2026 - January 2027
this is an upcoming stage for Pedestrian Bridges - Cudal and ManildraSite activities commence including piling and anchor footings
-
February 2027
this is an upcoming stage for Pedestrian Bridges - Cudal and ManildraOpen to public