Manildra Multi-Purpose Courts - February 2026

The relocation of the Manildra multipurpose courts is progressing well, with the project on track for completion in April 2026.

Asphalt surfacing has now been completed, and fencing works are finished except for the installation of the large gates. A request for quote has also been issued for the concrete footpath that will link the new courts to the Golf Club house.

Upcoming works include rectifying minor asphalt defects, painting and line marking the courts, commencing lighting installation in February, and constructing the connecting footpath.

Manildra Multi-Purpose Courts - February 2026

The relocation of the Manildra multipurpose courts is progressing well, with the project on track for completion in April 2026.

Asphalt surfacing has now been completed, and fencing works are finished except for the installation of the large gates. A request for quote has also been issued for the concrete footpath that will link the new courts to the Golf Club house.

Upcoming works include rectifying minor asphalt defects, painting and line marking the courts, commencing lighting installation in February, and constructing the connecting footpath.